Estimating Concrete for Canal Lining

PE Exam Practice Questions: Estimating Concrete for Canal Lining

June 20, 2023 by Anthony Fasano, P.E. Leave a Comment

In this article (and video above), we tackle a real-world scenario that could show up on the PE exam: Estimating concrete quantity for a canal lining. This question was created and solved by Engineer in training, Enrique Ivers, LEED Green Associate.

Question:

Construction documents call for a 500-foot-long canal, shown below,  to be lined with 6” of concrete for erosion control.  A 5% allowance is made for waste and over-excavation. How many cubic yards of concrete should be ordered?

Estimating Concrete

Explanation:

This problem has several steps and potential snags. Let’s think about it and then go through each one:

1)  We need to consider the cross-sectional area of the concrete at the base of the canal, the left leg, and the right leg.

2) We then must consider the distance the canal travels to find the volume.

 

3) Finally, we have to consider our waste factor.

The area of the left and right legs are equal. We’re given the height and told the slope of the legs is 1:1.

To find the hypotenuse, or the actual dimension of the leg, we must find the width:

Estimating Concrete

Estimating Concrete

Now we need to find the hypotenuse:

Estimating Concrete

We can now find the cross-sectional area of the lining:

Estimating Concrete

 

Next we calculate the volume of the lining:

The canal is 500 ft long, and we’ve calculated the cross sectional area above.

V=Area x Length

We must convert from cubic feet to cubic yards; there are 27 cubic feet in a cubic yard:

It would be tempting to take this 372.96cy and select answer B. After all, it is very close to 373cy, and the PE will expect us to round answers in this way.

BUT, don’t forget to take into account the whole problem. We’re told there’s a 5% waste factor.

Answer:

The correct answer is C.

This Episode Is Brought to You by PPI

PPIPPI has helped engineers achieve their licensing goals since 1975. Passing the FE and PE exams can open doors to career advancement and new opportunities. Check out PPI’s wide range of prep options, including Live Online courses, OnDemand courses, and digital study tools to help prepare you to pass your licensing exam here.

I hope you found this article helpful. In upcoming articles, I will solve some more PE exam practice problems and answer other questions from our subscribers. Pass the PE Exam videos will publish weekly, so be sure to click the subscribe button so you don’t miss something that could make a substantial difference in your exam result.

Lastly, I encourage you to ask questions in the comments of this video, or on this page and I’ll read and respond to them in future videos. So, if there’s a specific topic you want me to cover or answer, we have you covered.

I’ll see you next week… on Pass the PE Exam

Anthony Fasano, P.E.
Engineering Management Institute
Author of Engineer Your Own Success

Filed Under: Blog Posts, PE Exam, Videos Tagged With: Estimating Concrete for Canal Lining, estimating concrete quantity, PE Exam Practice Questions